Hesham Anwar Mohielden Forensic delay analysis Enquire
Fig. 01

Independent practice · Cairo

Which event actually moved completion?

I establish who caused construction delay and how much time it actually consumed — as an engineer-lawyer who has spent nineteen years building the very programmes that disputes are argued over.

AACE RP 29R-03 SCL Delay Protocol Primavera P6 FIDIC
Fig. 01 — as-built against baseline Completion slip: 16 days
Q1 Q2 Q3 Q4 Q5 Q6 Q7 38 d event on the driving path ENABLING PILING SUBSTRUCTURE SUPERSTRUCTURE MEP / COMMISSIONING 16 d BASELINE AS-BUILT DELAY COMPLETION
Illustrative. 38 days were lost at substructure; 22 were recovered downstream, so completion moved by 16. Lost time and lost completion time are different figures — separating them is the whole job, and the slip is the only one a tribunal will act on.
Instruction

Typical instructions

Four reasons a firm calls, and what each one needs.

Pre-claim assessment

Before anyone commits to a claim

An event has occurred. The question is whether it moved completion, by how much, and whether the record can prove it — answered before the client spends money on a claim that will not survive scrutiny.

Rebuttal

When the submission lands

An extension-of-time submission has arrived. It needs testing against the programme record, its causal chain checked, and a reasoned response prepared that separates entitlement from mere delay.

Second opinion

When an opposing expert is relied on

A report is being used to settle or argue the matter. Its method, its record base and its conclusions need independent review — and the review needs to be defensible in its own right.

Tribunal support

When the hearing is close

The schedule evidence must be presented clearly, consistently with the reports already served, and inside the tribunal's timetable — including the demonstratives that make a programme legible to non-engineers.

Method

Method

Five ways to answer the same question. The method is chosen, not assumed.

Which analysis is available depends on the record: whether the programme was updated contemporaneously, whether the baseline was accepted, whether the events can be isolated. That choice is made explicitly, in writing, before any time is quantified.

Time impact analysis
Prospective analysis of change events against the accepted programme, window by window, testing effect on the then-current critical path.
Window / contemporaneous
Period-by-period analysis that addresses concurrency, pacing and mitigation as events unfolded, using the updates actually issued.
As-planned vs as-built
Retrospective comparison of baseline against actual sequence and dates, to identify and measure where completion was lost.
Impacted as-planned
Modelled insertion of employer- and contractor-risk events into the baseline, to test individual and cumulative effect.
Collapsed as-built
Removal of identified delay events from the as-built programme — the “but-for” test of what completion would have been.
Reported under AACE International Recommended Practice 29R-03 (Forensic Schedule Analysis) and the SCL Delay and Disruption Protocol. Before any of the five is applied, the records are tested: contemporaneous, prepared for the claim, or reconstructed after it? That answer decides which method is available — and it is stated before the analysis begins, not discovered in cross-examination.
Independence

How I work

One matter, one lane. The wall does not move.

Never both. In a single dispute I act either as advocate or as expert and analyst — not both, not sequentially, not “for a limited purpose”. Independence is the product; an opinion with a stake in the outcome is worth nothing to the tribunal that has to weigh it.

No prior role, and full disclosure. An expert or analyst instruction is accepted only where I hold no advisory, advocacy or commercial role for any party, contractor or adviser connected to that dispute — and prior involvement is disclosed before appointment, not after.

Where a client needs both, the advocacy file goes to counsel and I remain on the technical side of the wall. Firms tend to find that arrangement useful rather than inconvenient: the analysis stays clean, and the advocacy is done by someone whose independence was never in question.

Why it is non-negotiable. The expert franchise is the scarcer asset, and one sustained challenge to independence ends it permanently. Advocacy can be referred on. An appointments record cannot be rebuilt.

Record

The record

Nineteen years of programmes. Before that, sixteen years of building them.

19Years in planning and project controls
16Years contracting, before consultancy
2Consultancies: Dar Al-Handasah, ECG
6Sectors: ports, aviation, buildings, highways, industrial, metro
Currently
Dar Al-Handasah (Shair and Partners), Cairo — since 2016. Independent third-party forensic schedule analysis resolving disputes between owners, consultants and contractors; schedule review and variance analysis on giga-projects; internal training in planning and forensic technique.
Previously
ECG — Engineering Consultants Group, 2007–2015. Head of the planning and cost control department; led claims and dispute resolution and contractual negotiation; administered FIDIC-based contracts; monitored contractor progress against approved measurement procedures.
Before 2007
Sixteen years contracting — project management and site delivery on metro stations, bridges, airports, hospitals, hotels, industrial plants and highway works in Egypt and Saudi Arabia. EPC bridge programme and contract administration under Parsons supervision, 2004–2006.
Qualifications
B.Sc Civil Engineering (1987) · LL.B (2012) · Professional Diploma in International Arbitration · MBA, Financial Management (2020) · IPMA certification · DBA in progress.
Appointments
CRCICA Registered Expert · Registered Arbitrator, Arbitration Ireland · Member, Society of Construction Law (UK) · Licensed Lawyer, Egyptian Bar Association · Certified Project Management Consultant Engineer, Egyptian Syndicate of Engineers.
Languages
Arabic — native. English — very good. Reports and correspondence in either language.
Sectors

Sector experience

The disputes come from the projects. So does the familiarity.

Ports and marine

Doha Port, Qatar · Tahya Masr Multipurpose Terminal, Alexandria, Berths 55–62 · Alexandria Chemical Terminal.

Aviation

Terminal Building 3, Cairo International Airport · Borg El Arab International Airport modernisation.

Buildings and hospitality

Katara Hills, Qatar · Cairo Festival City · Mall of Arabia · MADINATI Open Air Mall · Semiramis InterContinental · Le Méridien Pyramids · Dar Al-Fouad Hospital · Porto October.

Highways and infrastructure

Wahat–Frafrah 45 km, Abbasah–Zagazig 19 km and Al Hasana–Nakhil 40 km for the General Authority for Roads and Bridges, with associated roadway bridges.

Industrial and utilities

Abu Sultan Medical Union pharmaceutical plant · Jotun paint plant extension, Ismailia.

Metro and transport

Surface stations for the Greater Cairo underground network, with associated flyovers and bridges.

Contact

Contact

Instruct me on a matter, or test the analysis first.

Enquiries from law firms, contractors, consultants and employers are welcome. A first conversation usually establishes within twenty minutes whether the record supports an analysis — and if it does not, that answer costs nothing and saves a claim.